Awarded

Guardrail Package

Tender ID: 581208


Tender Details

Organisation:
Tender #:
MRC-2026-COCC-000063  
Status:
Awarded
Closing Date:
23 February 2026
Closing Time:
10:00 AM (Australia/Queensland)
Awarded Date:
07 May 2026

Tender Description

⁠⁠⁠INTRODUCTION

Mackay Regional Council (the Principal) requires the supply and installation of safety barriers at three Separable Portions within the Mackay Regional Mackay Regional Council area, as detailed below:

(a) Site one (1) – 29 Glenella Richmond Road, Glenella – Separable Portion 1

(b) Site two (2) – Langdon Lumburra Road, Dows Creek – Separable Portion 2

(c) Site three (3) – Chain Street, Mackay – Separable Portion 3

While the Contractor may elect to commence Works concurrently across all Sites, if a sequential approach is adopted, unless otherwise directed by the Superintendent, Works must commence at Site one (1) The Principal intends to award the Contract in its entirety to a single Contractor. No division of the Scope will occur, and no Contractor will have any claim arising from the Principal’s decision to award the Contract as a whole or not at all.

NATURE OF CONTRACT

The Contract Sum will be a Schedule of Rates (re-measurable) as described in the General Conditions of Contract (refer to ‘Part 4 Contract’).

All rates and quantities are to be checked by Tenderer. Any discrepancies shall be advised to the Principal during the tender advertising process (refer to Part 2 [2.] for how to lodge questions).

TIMING

The Contract is proposed to commence on 07 April 2026, and the Separable Portions must be completed as follows:

(a) Separable Portion 1 – 29 Glenella Richmond Road, Glenella

Date of Practical Completion: 04 May 2026

(b) Separable Portion 2 – Langdon Lumburra Road, Dows Creek

Date of Practical Completion: 08 June 2026

(c) Separable Portion 3 – Chain Street, Mackay

Date of Practical Completion: 06 July 2026


Location